|
JAMAICA
MORTGAGE BANK HOUSING DEVELOPMENT SEMINAR ON MARCH 26, 2002
PRESENTATION BY JEREMY BROWN
OF IMPLEMENTATION LTD ON FEASIBILITY
STUDIES; PRELIMINARY DESIGNS, COSTING AND CONSTRUCTION SCHEDULING.
Feasibility Studies
Feasibility studies are
dynamic and will be subject to many changes during the planning and
design stages of a housing project. They reflect the developer's
assumptions and knowledge at the time of their preparation. At the
pre-feasibility stage assumptions may be no more than
intelligent guesswork but a gradual 'hardening
of numbers' is achieved as designs proceed through the design stages.
Eventually a feasibility study will be supported by detailed pre-construction
budgets at the construction working drawings stage and by actual contract sums
after the tender or negotiation of construction contracts
A feasibility study should comprise :
- The development budget
-
Cash flow projection which with
minor adjustment is equivalent to a projected Profit & Loss
Account.
-
Market research information
establishing selling prices, estimates of demand, deposits and
installment structures and the developer's estimates on the pace
of sales.
- Risk analyses.
At the various stages of the design process -
schematic, design development and finally, construction working drawings, a
feasibility study should evaluate the viability of the proposed housing
development. After completing contract negotiations or after tenders have been
invited and returned, the developer should undertake a final review of the
feasibility study, and make the all important milestone decision whether to
proceed or abandon the project. This decision may be left to the lending
agencies
Much emphasis is placed on the developer's
ability to control development costs in line with budgets. However, I believe
insufficient emphasis is placed on their ability to sell and deliver housing
units and collect sales proceeds within the programmed time-frames. Many
schemes have failed because of an increasing interest cost burden directly
relating to the collection, rather than the expenditure, of money.
What determines feasibility or viability ? In
my opinion this is achieved by :
- Establishing a clear understanding
of your market and by
- Ensuring affordability
Affordability results when prospective home
buyers are able to qualify as borrowers for long-term mortgage loans. In
simple terms, monthly incomes must equal, or exceed, 3 to 4 times the monthly
mortgage commitment,
I have witnessed many examples of failed
housing schemes where the market was determined by development cost and not by
the 'market establishing development cost'. The market must always establish
development cost and feasibility studies must reflect this.
The majority of housing developments undertaken
in Jamaica over the past few years have occurred in the low- to lower-middle
income segment of the market. This undoubtedly arose as it is the largest
segment of the housing market with substantial unsatisfied demand. However,
this segment of the market is no more able to afford the purchase price of
homes than say the middle- to upper-middle income market. What has made the
difference encouraging developers to concentrate on the lower income market ?
The availability of long-term mortgage and short-term bridging finance at
substantially lower interest rates than prevail in the private capital
markets. This 'soft' or 'softer' financing is being sourced from institutions
such as the National Housing Trust and our host, the Jamaica Mortgage Bank
And what impact does this financing have ? - it
ensures affordability, it increases the ability and numbers of purchasers able
to qualify for mortgage loans. And affordability has resulted in the generic
term 'affordable housing'. I believe the term 'affordable housing' has
resulted more from creative financing and not necessarily because of 'cheap'
construction or 'low cost'.
Therefore, I am emphasizing that 'marketability
is principally driven by affordability'. Location, aesthetics, size, features,
services, all play an important role in buyers' perceptions and must not be
ignored, but there is no market, no effective or realistic demand, if that
market cannot afford the purchase price or cannot afford to meet the monthly
commitments.
It is interesting that recently, a housing
developer in the Portmore area announced a reduction in the number of
two-bedroom units they were proposing to build, substituting these units with
one-bedrooms. I'm certain this decision was driven by affordability and not by
the market preferring one-bedrooms
Therefore, as developers be aware of the market
you are attempting to satisfy, be cognizant of its income levels and establish
realistic selling prices based on affordability.
When your target market has been defined,
prepare a pre-feasibility study. A pre-feasibility study will assist in
providing a realistic assessment of what can or must be achieved in terms of
densities, sizes of units, infrastructure provisions and financing
requirements. It should incorporate statutory requirements, as a Planning
Enquiry should have been made, and reflect the inputs of the utility
companies. It can be completed even before the land has been acquired, i.e.,
the developer can enter into an option to purchase agreement, and should
certainly be completed before architectural and engineering designs are
underway.
The pre-feasibility study is a requirement of
and a prelude to the design brief and provides the developer with the
knowledge and information for instructing the design team as to what can
reasonably be afforded for inclusion at this stage. As I've already said, the
planning and design stages of a project are dynamic and many change are likely
to occur between the conceptual and schematic stages and the construction or
working drawings stage, including the distinct possibility of abandonment
A pre-feasibility study permits the developer
to undertake a number of risk or 'what-if assessments. For example, what is
the impact of phasing the development or the impact of delays? Or increasing
costs? The pre-feasibility study will reflect the impact of alternative
scenarios on cash flows.
PRELIMINARY DESIGNS AND
COSTING
The design brief, which emanates from the
pre-feasibility study, should instruct the architect on :
-
Site planning including densities.
Planning a subdivision is critical and requires careful
consideration and in many in stances can be the difference
between profit and loss of the statutory requirements for
amenity areas, building set backs, seeding, road reservations,
parking, water storage, sewage disposal etc.
-
The projected building or floor
area of units including number of bedrooms, bathrooms, patios
and parking.
-
The scope and price range of
finishes and specifictions, e.g., floor and wall finishes, types
of roof and finish, types of windows and door.
-
Details of recreational amenities
and scope of hard and soft landscaping.
The pre-feasibility study design
brief will assist engineers in defining engineering specifications
such as :
- Road paving.
- Kerbs and gutters.
- Electricity supply - above or
below ground.
In our generic housing development we now have
a pre-feasibility study and design brief with the design team properly
instructed by the developer. I would now like to look at the components of the
development budget and make a few brief comments based on the observations of
many years experience
1. Land Acquisition
a. Ensure you receive the proper legal
advice concerning limitations imposed by restrictive covenants, rights-of-ways
etc
b. Also seek advice on the sub-division
and issuing of splinter titles. If strata titles are involved there will be
restrictions on the ability to phase a development.
c. Future ownership of roads
and services - are these to be retained by the developer, handed
over to future purchasers or to the local authorities? What are
the legal implications and the mechanics ?
d. Boundary and topographical surveys are
essential. I have seen numerous examples of developers unwilling to commission
and pay for topographical surveys only to incur substantial cost over-runs
because infra structure works have been poorly planned. For example, sewage
disposal by gravity is less expensive than lift stations. Constructing a road
around a hill is cheaper than going through it !
e. Please instruct surveyors to identify
major trees and existing landscaping worth retaining. These have value and
will increase marketability.
f. Agree with the civil & structural
engineer whether soils investigations are needed. Do not skimp on the number
of boreholes - you may regret it later. I have.
g. Most important - walk the site and get
a ‘feel’ for it. Are there security or noise problems which must be
addressed ?Visit the site during a heavy rainfall. How does it drain ? Are
there gully courses which have been filled ? These may cause foundation
problems.
2. Professional Fees
a. A developer needs professional advice
and you get what you pay for. Increasing the input or quality of your
professional team, which may add fees equivalent to say 3% of construction
cost will have an impact of approx. 2% on selling price. I would rather reduce
my profit margin by this amount and proceed with greater confidence and less
risk.
b. How many developers retain the
services of a landscape architect ? For the equivalent of say 2% of selling
price a developer may receive 4% in value in terms of sales promotion and
marketability.
3. Infrastructure or Siteworks
a. This is an area of the development
budget most likely to incur cost over-runs. Don’t unreasonably short change
the necessary inputs such as the topographical survey.
b. Understand the design and budgetary
implications of statutory requirements and the provision of utilities. JPS may
charge a fee for bringing their high voltage supply to the site but a
substantial element will be refundable, usually after 3 years. What do you
budget ? Based on your approval, the Parish Council may take over the roads
and other public areas but impose a maintenance cess, usually for a one year
period. Is this budgeted ? I know of housing schemes and subdivisions where
Parish Councils have refused to take over and accept responsibility for roads
as they complain they were not constructed according to their specifications.
Now years and even decades later these roads are in a deplorable condition
with the disputes still unresolved.
4. Building Construction
a. In my experience, and as a rule of
thumb, building construction should not exceed 55% of selling price. If it
does then the project has an increased risk of not being viable.
Alternatively, the developer may be prepared to accept a reduction in their
profit margin, which also increases their risk factor as the margin will be
eroded faster by cost over-runs.
b. In Jamaica, and I’m sure in many
other countries, we believe a construction ‘system’ exists which will
substantially reduce construction costs and is the panacea towards achieving
‘affordable’ housing. I don’t believe in this. But I am negating the
importance of ‘systems’ construction. Quite the opposite.
If you accept the reasonableness of my estimate
that in a typical housing development construction cost should not exceed 55%
of selling price, and I can provide a percentage build-up of selling price,
the structural component of the building construction cost probably amounts to
approximately 40%..
Therefore, the typical ‘system’, which
affects the method of building the structure, directly impacts less than 30%
of typical selling price , i.e, roughly 40% of 55%. Controlling the cost of
the structure, equivalent to 30% of selling price, is important and not to be
ignored but it is not the solution to affordable housing.
Good management is. ‘Systems’ construction,
in my opinion, enhances opportunities for efficiency and effective management.
Some ‘systems’ allow the contractor to undertake a substantial element of
their construction input in ‘factory-type’ environments where supervision,
inventory management, cost control, scheduling, adherence to specifications
and quality control are better managed.
However, if these elements of good management
can be and are transferred to the construction site then there is no reason
why ‘traditional’ construction cannot be as efficient and less susceptible
to cost over-runs and delays.
‘Systems’ construction has an important
role to play but is not appropriate for all types of development. Invariably,
cost over-runs and delays can be traced back to poor management, including :
The poor quality of information provided the
contractor - lack of detail on drawings or in specifications causing
procurement delays and claims. ‘Systems’ construction has the advantage of
requiring all information to be available up-front prior to production
commencing and allows no, or minimal, change thereafter. This is a big plus
and enforces discipline on professionals. Ineffective supervision resulting in
non-productive labour and loss and wastage of materials.
The necessity to re-do construction works as
poor quality workmanship is not identified early enough.
Inability to adequately schedule the various
elements of the construction process and properly resource these elements. I
will discuss this in a few minutes.
c. The developer’s decision to tender
or negotiate the construction contract should be made early in the design
stage. With negotiation, it is advantageous for the contractor to join the
project team and provide their ‘value engineering’ input into the design
process. However, competitive tendering ensures transparency and should
provide the assurance that the best possible price has been obtained.
d. Ensure designs and specifications are
complete. As previously mentioned, this is the probable cause of the majority
of contractor’s claims for extensions of time with compensation.
e. The developer must decide which form of
construction contract is appropriate. Increasingly, my office does not use the
local JCC form of contract preferring to use one of the forms developed by the
American Institute of Architects. Special Conditions of Contract must be
drafted to adapt the forms to local conditions.
f. In today’s relatively low
inflation environment, clauses permitting escalations in the
construction contract sum can be limited. With contract sums
stated in Jamaican dollars, we generally write contract conditions
accepting fluctuations in labour costs and cost adjustments
arising from exchange rate changes to be passed on to the owner or
developer.
5. Landscaping
a. No comment other than I wish more
attention was paid to both hard and soft landscaping and a recognition of its
advantages
6. Financing Costs
a. Legal fees and costs on loan
security documentation must be budgeted.
b. Also, commitment fees and
interest costs on loans. Understand the terms and conditions
contained in commitment letters and loan agreements received from
financial institutions. Some will have cost implications.
c. Understand the implications of the Real
Estate (Dealers & Developers) Act. The use of purchasers’ deposits is
restricted by Law with cash flow implications.
d. Interest charges. I raise a big red flag.
There are so many risks and pitfalls which can cause substantial increases in
interest costs. These have the potential to reduce or eliminate a developer’s
profit margin. Some are:
The cost of delays in completing construction
works and achieving Practical Completion which are irrecoverable from
liquidated damages imposed on the contractor.
Inability to sell units within the time-frame
contemplated.
Delays in collecting sales proceeds - it is
essential to monitor the mortgage lending agencies and their and your
attorneys-at- law. Also monitor the effective ness of the Registrar of Titles
in registering Transfers and mort gage loans. Never forget that the delays of
third-parties increase interest costs.
Cash flow projections are very important. They
will reflect a project’s phasing and the implications of this phasing. Some
infrastructure costs may be impossible to phase such as the cost of a sewage
treatment plant. The cash flow will reflect the developer’s estimate of
units to be sold over a defined period. The developer’s equity input will be
reflected on the cash flow projection with most financial institutions
insisting on equity funding being expended before loan financing can be draw
down. Some institutions will only fund ‘hard’ costs.
7. Developer's Overheads.
a. Property taxes on the land prior to
purchasers assuming responsibility
b. Cost of statutory approvals.
c. Insurances not carried by contractors. All
Risks insurance on unsold units after Practical Completion has been granted or
on units where legal possession has not been delivered to.
d. Security costs incurred by the developer.
8. Selling Expenses
a. Advertising and promotion.
b. Commissions paid to real estate
brokers.
c. Legal fees for preparing sales
agreements.
d. Legal fees and costs on
Transfers including Stamp Duties, Registration Fees and Transfer
Tax.
9. Developer's Profit Margin
a. The most flexible of all
elements of the development budget and the only element likely to
decrease and not increase.
b. Factors which influence the
amount of the developer’s profit margin are : Strength of the
housing market - buyers’ or sellers’ market.
The amount of the developer’s equity
contribution.
Influence exerted by financing institutions
such as the NHT and JMB
c. I would expect margins in the 8% to 12%
range, calculated on total development cost. These percentages do not reflect
Return on Investment as an 8% margin on total development cost may equal a
Return on Equity Invested of 40% or more per annum.
d. Do not begrudge the developer their profit
margin. There are few business ventures so fraught with risk and uncertainty.
The successful developer will reduce their exposure to risk and uncertainty to
a minimum and will frequently update their development budgets, cash flow
projections and feasibility studies to reflect the most recent and current
conditions.
10. Selling Price
a. The elements of the development budget at 1
to 9 discussed above equal selling price. Selling price in the main is
inflexible and can only be increased if allowed by the developer’s sales
agreement. If demand is strong and a scheme is phased, later phases may permit
selling prices to be increased. But the opposite may also prevail, causing a
reduction in selling prices or the abandonment of later phases.
CONSTRUCTION SCHEDULING
My business is project and
construction management and one of the most useful tools we have is
computer software which facilitates scheduling or programming.
It is surprising how few developers
or contractors avail themselves of the opportunities afforded by the
use of this software. Drawing a line across a time scale for a small
number of tasks, creating a Bar or Gantt Chart, means little. We now
develop schedules with thousand of tasks all of which are programmed
with predecessor or successor linkages. Critical tasks are
identified allowing us to concentrate on those areas most likely to
delay construction. We try and avoid delays by investigating
alternative scheduling.
A major advantage of construction
scheduling is that it forces the developer, contractor or
construction manager to ‘think a project through’ in detail.
Apart from identifying critical paths, which are likely to change as
schedules are updated, milestone dates are identified which may be
incorporated into construction contracts. For example, completing an
early phase of construction by a milestone date may be a
pre-condition for being awarded later phases of construction.
We partially resource these
construction schedules. Programming tasks on paper is easy and
completing a contract on time can be achieved by artificially
shortening durations. But are the resources available to complete
these tasks within the shortened time-frames contemplated.
My experience shows that the most
critical resources to identify are equipment, skilled trades and
procurement requirements.
We have worked on projects where resourced
construction schedules have identified :
i. In Dominica - the contractor had
insufficient concrete batching equipment on site to meet their concrete
requirements.
ii. A contractor had insufficient
back-hoes on site to excavate building foundations in keeping with
their programme. This critical activity would have delayed
Practical Completion.
iii. Inadequate numbers of
carpenters, masons, steel men, tilers, painters - to achieve the
desired programme.
iv. Procurement delays caused by
the failure of the developer’s project team to detail or specify
materials because they failed to anticipate availability,
importation requirements, customs delays and delivery to site.
The construction schedule must be periodically
updated with completion percentages incorporated. Computer software permits
the tracking of progress with uncompleted tasks rescheduled to automatically
commence immediately after the update, but still recognizing and retaining
their linkages. Delays in construction schedules usually compress trades,
particularly finishing trades, within shorter time-frames. This is referred to
as the ‘stacking of trades’ and requires their numbers to be identified
and sourced.
A detailed construction schedule assists
contractors, construction managers, architects and engineers to evaluate
claims for extensions of time and also claims for acceleration and stacking of
trades. It is ironic that many contractors have become increasingly
sophisticated in developing and submitting claims but have not yet adopted the
sophisticated tools to assist and enhance their management techniques.
|